These photos come from one of our own nail salon build-outs, not a stock library. They show the part of a salon nobody sees once it opens: the drain lines for the pedicure chairs, set under the concrete slab.

Salon inspiration

Images in this video

Pedicure drain manifold set under the slab (BAT job site)
Pedicure drain manifold set under the slab (BAT job site)
Drain branches for a pedicure group, before backfill (BAT job site)
Drain branches for a pedicure group, before backfill (BAT job site)
Drain stub-ups for a row of pedicure chairs (BAT job site)
Drain stub-ups for a row of pedicure chairs (BAT job site)
Stub-ups spaced to the pedicure chair layout (BAT job site)
Stub-ups spaced to the pedicure chair layout (BAT job site)
Wye fittings joining the pedicure drains (BAT job site)
Wye fittings joining the pedicure drains (BAT job site)
Main drain trench running across the salon floor (BAT job site)
Main drain trench running across the salon floor (BAT job site)
Crew laying the main drain line (BAT job site)
Crew laying the main drain line (BAT job site)
Branch drains with cleanout access (BAT job site)
Branch drains with cleanout access (BAT job site)
Sink drain connection at the corner (BAT job site)
Sink drain connection at the corner (BAT job site)

Real photos of projects built by BAT.

BAT Build USA

Design notes

Why the pedicure plumbing comes first

In most tenant spaces the existing slab has one sewer line along the back or side of the unit. Every pedicure chair needs its own drain, and those drains have to reach that sewer line with the right slope. That means saw-cutting the concrete, digging a trench, laying pipe and patching the floor before any flooring, cabinets or chairs go in. If this step is wrong, the only fix later is to break the new floor open again.

Saw-cut trenches follow the chair layout

The trench lines in these photos were cut to match the final pedicure layout, not the other way around. Before cutting, the chair model has to be chosen, because each brand puts its drain and water connections in a slightly different place. Once the chair positions are fixed, each drain stub-up is set where the chair's drain will land, as you can see in the row of stub-ups along the new wall framing.

Wye fittings tie each chair into the main

Each pedicure branch joins the main drain with a wye fitting, which turns the flow in the direction of the main instead of hitting it at a right angle. Plumbing codes typically require drain pipe of this size to slope about 1/4 inch per foot so water and debris keep moving. Long runs to a far sewer line use up depth quickly, which is one reason a pedicure row close to the existing sewer is cheaper to build.

Vents, cleanouts and the sink corner

Drains also need venting so the traps do not siphon dry and let sewer gas into the salon. In these photos you can see vent stubs rising at the wall lines and cleanout points on the branches, which give a plumber access if a line ever clogs. The corner sink drain is set the same day so the whole system can be inspected at once.

Protecting the rest of the space

Trenching a salon floor creates dust, debris and open cuts next to new wall framing. On this job the trenches run parallel to the metal studs, with the cut concrete set aside so the patch can be finished flat. Keeping the rough plumbing tight to the walls also leaves the center of the floor clear for the client path and the manicure stations that come later.

Inspection before the floor is closed

In most jurisdictions the underground plumbing has to be inspected, and often pressure or water tested, before the trench is backfilled and the concrete is patched. Owners should plan the schedule around that inspection. A missed inspection can mean opening the floor again, which costs time on a lease that is already running.

What owners should decide before construction

Choose the pedicure chair model and count, confirm where the existing sewer line runs and how deep it is, and decide where the water heater, restroom and mop sink will go. With those answers the layout can keep the plumbing short. This is the part of the plan we draw in 3D with the trades, so the drain, water and power locations are agreed before anyone cuts concrete.

These are real photos and video from a BAT Build USA job site. Plumbing work must follow the code adopted where your salon is located and be done by licensed trades. Call +1 770-378-9163 / +1 470-984-7776 for a free 3D design consult.

FAQ

Common questions

How many pedicure chairs can one drain line serve?

It depends on the pipe size, the slope and the local plumbing code. Most layouts run one main under the pedicure row with a separate branch and trap for each chair, sized by the plumber to the chair maker's requirements.

Do I have to cut the concrete floor for pedicure chairs?

Usually yes, unless the chairs use pump-out drains or sit on a raised platform. Most salons trench the slab so each chair drains by gravity to the existing sewer line.

When is the underground plumbing inspected?

In most cities the inspector checks the underground drains before the trench is backfilled and the concrete is patched. Your contractor should book that inspection in the schedule.

Can I move the pedicure row later?

Moving it means cutting the floor again and rerouting the drains, so it is expensive. Settle the chair layout and model before construction starts.